Update: 10.16.2025

Electrical contractors have hit substantial completion. 

Crosswalks will be poured at the Broadway intersections on Thursday and will remain closed until Monday.

Painting will begin next week.

 

Update: 10.13.2025

Porter Brothers and the electrical contractor continue to work on punch list items. 

Asphalt has been applied and the contractors are currently in the process of building the concrete crosswalks.

 

Update: 10.09.2025

Porter Brothers is completing asphalt installation this week. The roadway will be open to traffic immediately after. 

Striping will begin in 10-12 days. This will include the parking places. 

Landscaping has reached substantial completion, with the contractor continuing to maintain the plants. 

A decorative arch and umbrella installation will begin next week in Market Alley. 

Question title

Have a comment regarding the current construction? Please enter it here!

Closed for Comments

Question title

What would you have done different with this project?

Closed for Comments

Question title

Do you have a favorite part of the design of the square?

Closed for Comments

Northern part of square